At the time of financial close for the Veja Mate offshore wind farm, the project’s grid connection solution was confirmed as using the existing BorWin2 offshore substation in the German North Sea. The 400–402 MW wind farm, located around 95 km northwest of Borkum, will export its approximately 1.6 TWh per year of production via BorWin2, which is managed by transmission system operator TenneT. This arrangement fixes BorWin2 as the designated connection point for Veja Mate, integrating the project into the German high-voltage network under TenneT’s offshore grid programme and enabling the non-recourse financing structure agreed with a consortium of lenders.