As of 30 September 2025, Terna reports substantial construction progress on the Tyrrhenian Link’s cable connections and converter substations. Civil works for the construction of cable trenches and laying of the first and second poles are well advanced in Sicily and Campania, and at the converter substations the structural components of the main buildings are being completed, with production of main equipment progressing, the prefabricated control building assembled, and valve rooms and DC buildings under assembly at Eboli and Termini Imerese.