Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
TuNur’s 2024 project information for the TuNur Italy 2,000 MW HVDC transmission line between southern Tunisia and Montalto di Castro, Italy, sets out a development timeline with a feasibility phase scheduled for 2024–2025. This feasibility stage is planned as the first step before design and engineering, permitting and authorisation, financing, and construction leading to operation from 2034.