Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +10yr (Apr 2026): 2017 statements implied first exports to Europe via Malta by 2021, contingent on construction from 2019. TuNur Malta appears in ENTSO‑E TYNDP 2024/2026 as a new merchant project at feasibility, and industry digests such as Warwick HVDC (Oct 2024) still describe the scheme as in feasibility with no construction. With a late‑2020s construction start and roughly a 3‑year build, first power shifts to around 2031, later than the original 2021 target. --- TuNur indicated that for the first 250 MW phase of its Tunisia–Malta export scheme, it was targeting delivery of power to the European grid via Malta by 2021, implying first electricity exports on the dedicated HVDC link in that year.