Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
System testing and commissioning of the power-from-shore solution for Troll B and Troll C, including transmission, distribution and power management systems, were effectively completed before power from shore was turned on. Equinor’s 11 September 2024 news release reports that on 7 September Troll B and C became partly powered from shore via the new Kollsnes-to-Troll B and Troll C cable system, with new electro modules and platform systems in operation. Achieving stable partial electrification implies that installation, system integration, and commissioning tests had been carried out successfully by 7 September 2024.