Troll A 1&2 entered commercial operation on 1 October 2005, when the 88 MW HVDC Light power-from-shore system began delivering electricity from the onshore rectifier station at Kollsnes to the offshore Troll A platform via approximately 70 km of subsea cable at plus or minus 60 kV. This was the world first HVDC Light installation to an offshore platform, replacing gas turbine-driven compressors with electrically driven units. Testing had been completed in February 2005, with the two compressor units brought into operation in early October. The system was delivered by ABB (now Hitachi Energy).
The Troll A 1&2 HVDC Light power-from-shore link between the onshore converter station at Kollsnes and the Troll A platform in Norway was successfully completed and commissioned in 2005, providing 88 MW of transmission capacity at ±60 kV via four 70 km submarine cables to supply offshore compressor power.
In 2002, Statoil (now Equinor) awarded Hitachi Energy (then ABB) a contract to deliver the world’s first power‑from‑shore HVDC Light transmission system to the Troll A platform, referred to as Troll A 1&2. The award covered the onshore rectifier at Kollsnes and the offshore inverter equipment on Troll A, enabling ±60 kV HVDC Light power transmission over roughly 70 km of submarine cable from the Norwegian grid to the offshore gas platform.
| Norway | Norway | |
|---|---|---|
| Landfall | Kollsnes (onshore, near Bergen), Norway | N/A |
| Grid Connection | Troll A offshore inverter / converter station (Troll A platform), Norway | — |
Norway
Norway