Foundation InstallationOffshore Substation Installation
Lifecycle Stages:
Construction
Quantities:92 foundations, 2 offshore substations
Contract Details
Description
MPI Offshore was contracted to install the offshore foundations package at Triton Knoll, described as 92 foundations, and to install the project’s two offshore substations.