Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Triton Knoll Offshore Wind Farm achieved first power in early March 2021, following the successful installation of the first of its 90 offshore wind turbines in January 2021 and the commissioning of its transmission system, including offshore substations, export and onshore cables, and the onshore substation. The RWE-led project completed the necessary commissioning activities on the transmission system to enable export of electricity from the 857 MW wind farm to the UK National Grid for the first time, despite challenges posed by the Covid-19 pandemic.