Following its CfD success, Triton Knoll’s owners stated that a final investment decision was expected in mid‑2018, alongside completion of financing arrangements for the approximately £2 billion capital investment required for the 860 MW offshore wind farm off the Lincolnshire coast. The developers indicated that achieving this FID would allow full onshore construction to start shortly after and offshore construction to commence in 2019–2020.