Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 20 June 2018, Triton Knoll’s developer awarded J. Murphy & Sons a £100 million contract for onshore substation construction and cabling works. This package covers the civil and electrical works for the new onshore substation near Bicker Fen and associated onshore export cabling that connect the offshore wind farm to National Grid, assets which are subsequently included in the Triton Knoll OFTO transmission system.