Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Commissioning of the Triton Knoll offshore transmission assets was completed in February 2021, and first generation over the system occurred on 26 February 2021. The completed transmission assets, including the offshore substations and export cables, began exporting power from the Triton Knoll wind farm towards the onshore grid from this date.