Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 2021, construction of the Triton Knoll offshore transmission assets was reported as complete, implying completion of installation of the two offshore and two onshore 220 kV export cable circuits, offshore substations, and onshore substation ahead of commissioning, which finished in February 2021 and first generation on 26 February 2021.