Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Over 19–20 August 2020, Triton Knoll completed installation of its two 50 km long 220 kV subsea export cables linking the offshore substation platforms to the onshore electrical network near Anderby Creek. Boskalis, working with NKT, laid and plough‑buried both three‑core export cable circuits, and NKT finished jointing the final length from the vessel Olympic Zeus, finalising the offshore export cable system that will transmit power from the wind farm to shore.