In late February 2025, HEP ODS’s NPOO PKB core team met in Split and agreed the implementation schedule for several submarine cable sections, including the 20 kV PKB Tribunj–Logorun–Kaprije link (8,150 metres). The plan set working windows from 1 April to 15 June and from 1 September to 1 November 2025, with works on the Tribunj–Logorun–Kaprije section planned to start in May and be laid by mid‑June, ahead of the tourist season.