Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
HEP ODS planned to start laying a new 20 kV submarine cable section between Tribunj on the mainland, Logorun Islet and Kaprije Island (PKB 20 kV Tribunj–Logorun–Kaprije, 8,150 metres) in May 2025, as part of its “Podmorski kabeli u distribucijskoj mreži za napajanje otoka” project, with works scheduled to begin in May and be completed by mid‑June, subject to sea and other conditions.