Significant progress or notable issue
According to a 24 June 2025 news release from HEP Group, HEP ODS teams from Elektra Šibenik and Elektrodalmacija Split successfully completed laying a replacement 20 kV submarine cable on the Tribunj–Logorun–Kaprije route (8,150 m). The article states that the replacement cable has been laid, indicating that submarine cable installation works for this section were underway and effectively completed by that date.