Trianel Windpark Borkum II · 200 MW54.04°N · 6.47°E · 45 km offshore
Project notessourced · 1 document
Trianel Windpark Borkum II is the 200 MW, second-stage extension of the municipal Trianel Windpark Borkum cluster in the German North Sea, sited roughly 45 km north of Borkum. The project was developed to expand generation capacity while re-using the park’s pre‑existing offshore substation and grid connection infrastructure, reducing the need for duplicated platform works and enabling a more compact export strategy to the DolWin Alpha converter. Construction began after a 2017 finance close and the programme advanced through monopile foundation installation, inter‑array cabling and turbine installation over 2018–2020. The project encountered timetable risk following the insolvency of the initial turbine supplier, which delayed delivery and commissioning into mid‑2020, but the owners and contractors managed re‑sequencing and logistics to complete the build. Trianel Windpark Borkum II is notable as a municipally led offshore development that pooled many small utility investors and used an optimised shared‑infrastructure concept with the first phase. The financing and contracting approach attracted attention at the time for securing low margins on offshore project debt. Operationally the farm exports its AC output via export cables to the DolWin Alpha HVDC converter for onward transmission to shore. The project plays a strategic role in regional offshore build‑out by demonstrating reuse of park infrastructure and municipal investor coordination in German offshore wind.
Basic information
10 fields
Also Known As
Borkum West II Phase 2 · Trianel Windpark Borkum Phase 2 · Trianel Wind Farm Borkum II · Trianel Windpark Borkum 2 · TWB II
Phase‑2 (TWB II) uses monopile foundations; water depths in the site are ~25–35 m and monopiles were driven/installed with ~30 m embedment. Turbines: 32 × Senvion 6.2/6.33M152.
Lease & Site Conditions
5 fields
Lease reference
pre-FEP
Lease area
56km²
Water depth
25–35m
Distance from shore
45km
Operations & maintenance
O&M comments
Sources reference turbine O&M arrangements and substation maintenance: Siemens Gamesa is cited as winning an offshore service contract for the Senvion turbines (Trianel press items) and other reports note Deutsche Windtechnik taking turbine service; the park's offshore substation operator IWB has a service/maintenance relationship with Omexom. Sources do not explicitly state a primary O&M base (port) or SOV usage.
Connected Projects
1 link
Grid connection
DolWin1 — Wind farm connects to separately-owned grid project 'DolWin1' (link set on candidate at promotion).
Cable Specifications
2 fields
Trianel Windpark Borkum II Array Cables
33 kV MVAC
System:33 kV MVAC
Burial depth:
Inter‑array (park internal) medium‑voltage cables were laid from the turbines into the shared offshore substation via the turbine foundations and then buried in the seabed (“in die Gründungen eingezogen” and...