Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
RWE’s 19 October 2023 press release on appointing Fugro for the Thor geophysical survey states that the UXO campaign for the Thor offshore wind farm will run until December 2023. Subsequent project updates show later offshore construction works starting on schedule in 2025, implying that the UXO survey campaign was completed by December 2023 as planned, although the exact day is not specified.