Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
RWE’s Thor project information page lists “Installation of subsea cables” under the 2025 project milestones and notes that a consortium of Hellenic Cables and Jan De Nul manufactured and installed about 60 km of export cables along the 30 km route from the offshore wind farm to shore, plus inter‑array cables and onshore cables. Additional trade‑press reports show export cable pull‑in completed by mid‑2025. This confirms that export cable installation had started and was underway in 2025, though the precise start day is not stated.