Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 5 July 2025, it was reported that Jan De Nul had completed the cable connection for Thor by finishing the offshore and onshore maneuvers required to lay and pull in the two main export cables from the Thor offshore wind farm site, located 22 km off Denmark’s North Sea coast, to the Danish mainland. With these works finished and the cables already onshore and in place, the export link is physically installed and positioned to eventually transmit up to 1,080 MW of renewable power to more than one million Danish homes once the project is fully commissioned.