On 23 February 2015, the intertidal joint of the South Export cable C1 in the Thanet OFTO transmission system failed, causing a significant outage on the export link connecting the Thanet Offshore Wind Farm to shore. This failure at Thanet OFTO, occurring just days before a separate export cable loss at Gwynt y Môr, was highlighted in industry discussions as contributing to insurer concerns about continued coverage for offshore transmission cable risks.