Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In a 2009 technical assessment for Ofgem, Thanet Offshore Wind Limited (TOWL) indicated that the Thanet offshore transmission assets were planned to complete construction by early 2010 and to be fully commissioned by 31 March 2010, at which point the full 300 MW Transmission Entry Capacity (TEC) for the Thanet wind farm would be available via the OFTO connection to Richborough 132 kV substation.