Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 16 September 2021, Solstad Offshore’s vessel Far Sapphire had completed installation of the inter-array power cable linking the newly installed TetraSpar floating wind turbine at 200-metre water depth to the Zefyros hub and existing 22 kV grid interface point to Karmøy. This dynamic cable, supplied under contract by Unitech, established the subsea grid connection so that the demonstrator could export power to shore via the METCentre test site.