Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
National Grid has offered the Tarchon Energy Interconnector a grid connection at the proposed East Anglia Connection Node (EACN) 400 kV substation in Tendring, Essex, establishing the intended UK grid connection point for the 1.4 GW GB–Germany interconnector. This offer defines where Tarchon’s onshore infrastructure would plug into the National Electricity Transmission System once built.