Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
Suurhiekka Offshore Oy submitted an application on 11 September 2014 to the Regional State Administrative Agency of Northern Finland requesting that the deadlines in water permit decision 10/11/2 for the Suurhiekka offshore wind farm be extended by three years for starting construction and by ten years for completing the project, citing the project’s large scale, complex coordination and demanding financing conditions.