On 18 December 2015, the Regional State Administrative Agency of Northern Finland approved Suurhiekka Offshore Oy’s request to extend the implementation period of the Suurhiekka offshore wind farm’s water permit, setting new deadlines that required construction to begin by 10 May 2019 and all works to be completed by 10 May 2029, after which the permit would otherwise be deemed lapsed.