Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Stromar targets turbine installation in 2033, between foundation deployment in 2032 and first power in 2033. As a 1-1.5 GW floating wind farm with c.65-100 floating turbines using tow-to-port hook-up onto previously deployed floating substructures, turbine installation typically follows foundation pre-installation by 6-12 months and precedes first power by 6 months in a typical floating-wind build cadence. Year precision reflects phase-level scheduling on the developer's website.