Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 8 September 2025, Van Oord had finished installation, termination and testing of approximately 360 km of inter-array cables at Sofia Offshore Wind Farm, successfully proving the collection system that connects the 100 turbines to the offshore converter platform prior to full project commissioning.