Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Geotechnical surveys for Sofia’s export cable route were scheduled to start in March 2020, to be undertaken from the vessel Despina using cone penetration tests and vibrocores over up to a month to inform final route selection, landfall location and cable installation methodologies.