WNoO #017/2026 — as-built 2026-04-20 Progress: foundations 100/100; inter-array cables 109/109; OCP commissioning active; WTGs 85/100 (Δ +5 vs prev WNoO). This period: WTGs installed L15, K15, J15. OCP commissioning continues with Valaris 248 jack-up alongside; PSV pool active. Forecast next 7 days: WTGs M15, S15, T15 (Trip #15). Active fleet: TIV Wind Peak; SOVs Acta Centaurus, Austri Enabler, Rem Power, Purus Power, IWS Seawalker; CTVs FOB Swath 9, FOB Swath 10, MHO Gurli, Seazip 9; PSVs at OCP Valaris 248, Highland Knight, Dina Merkur, Dina Supporter, Dina Supplier, Dina Scout, BOS-Pool, BOS-Base; ERRVs Putford Jaguar, Glomar Baltic; Buoyage Kingdom of Fife. Source: WNoO #017/2026 dated 28 April 2026, RWE Renewable UK Wind Service Ltd.