Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The official Sofia Offshore Wind Farm website’s offshore construction timetable states that in “Late 2025” the offshore converter platform is completed and “First power generated by the wind farm.” This places first export of electricity via the Sofia HVDC link to National Grid’s Lackenby substation in late 2025, later than the original Q3 2025 expectation but clearly achieved before early 2026. As no exact commissioning date is published, the milestone is confirmed approximately as 2025‑12‑31.