WNoO #017/2026 — as-built 2026-04-20 (Sofia OFTO scope) Progress: HVDC export cable installed (Apr 2025); OCS structurally complete; OCP commissioning active (Valaris 248 jack-up programme since Oct 2025, NTM 034/2025); 400 kV HVAC connection to Lackenby in place. This period: OCP commissioning continues with Valaris 248 jack-up alongside; PSV pool resupplying the platform throughout the week; ERRV cover maintained. Forecast next 7 days: Continued OCP commissioning programme; no transmission asset state change expected. Active fleet: Specialist Valaris 248 (jack-up at OCP); PSVs at OCP BOS-Pool, BOS-Base, Dina Merkur, Dina Supporter, Dina Supplier, Dina Scout, Highland Knight; ERRVs Putford Jaguar (NTM 001/2026), Glomar Baltic (NTM 008/2026). Source: WNoO #017/2026 dated 28 April 2026, RWE Renewable UK Wind Service Ltd (Sofia OFTO scope; same notice covers paired OWF — see Sofia OWF construction_update 69fc6b3501bb3da3fc9e5082).