Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
A second oil-impregnated, paper-insulated 35 kV submarine cable on the Hiiumaa–Saaremaa route between Pammana and Emmaste in the Soela Strait was installed in 1982, supplementing the original 1974 cable in providing the island interconnection.