Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Equinor and partners Vår Energi, LOTOS and KUFPEC took the final investment decision in mid‑2020 to partly electrify the Sleipner field centre, enabling power‑from‑shore via a new 28 km high‑voltage cable from Gina Krog as part of the Utsira High area solution that will also supply the Gudrun platform and other tie‑in fields. The Sleipner power‑from‑shore investment was set at about NOK 850 million, supporting emission reductions of over 150,000 tonnes of CO₂ per year from Sleipner within the wider Utsira High electrification scheme.