Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 26 March 2019, the transmission system operators Energinet and Statnett submitted a joint application to introduce implicit handling of grid losses on the Skagerrak interconnector between Norway (NO2) and Denmark (DK1), which includes the Skagerrak 1 and 2 HVDC links. The proposal analyses the socio‑economic effects of modelling a 3.8% loss factor for the Skagerrak interconnector directly in the Euphemia day‑ahead market algorithm and outlines an implementation plan leading to functionality testing in late 2019 and early 2020.