Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By 1977, both Skagerrak 1 and Skagerrak 2 cables were commissioned and in service as a bipolar HVDC scheme between Kristiansand in Norway and Tjele in Denmark, giving the Skagerrak 1 & 2 interconnector its full rating of about 500 MW under the ownership of Statnett and Energinet and marking the start of full commercial operation.