Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In December 2024 NVE issued a decision to extend the deadline for commissioning (idriftsettelse) of Statnett’s Fensfjorden submarine cable project between Iledalsvågen and Mongstad, adjusting the licence conditions to reflect the updated construction schedule.