Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Statnett planned to resume onshore construction for the Fensfjord cable project on 12 May 2025 at Mongstad, restarting land-based works after a 2024 stoppage as part of installing a new 7.7 km, 420 kV cable set across Fensfjorden to double capacity between Haugsvær and Lindås; the land works are being carried out by local contractor Nordhordland Grunn og Betong (NGB).