Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Statnett planned an offshore site-preparation campaign ahead of the originally scheduled 2024 cable installation, involving placement of an estimated 60–80 concrete mattresses over about 1.2 km of seabed in the approach to Iledalsvågen to stabilise soft sediments and prevent the new Fensfjorden cables from sinking into the seabed.