Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 1 December 2021, Ofgem took a decision on the ‘efficient cost’ of the Shetland–Caithness subsea HVDC interconnector developed by SSEN Transmission, determining the level of project expenditure considered efficient for regulatory purposes and thereby underpinning the project’s cost recovery under the GB transmission regime.