Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Shetland Islands Council issued Marine Works Licence 2020/011/WL for the Shetland HVDC Link marine works at Weisdale Voe. The licence requires that, prior to works commencing, a Construction Method Statement and an Operations and Maintenance requirements document be submitted to and agreed in writing by the Planning Authority, covering cable specification, construction timing and phasing, vessel management, and pollution prevention; these conditions are noted as being addressed by the Shetland HVDC Link Construction Method Statement and the Inspection, Repair and Maintenance Plan.