Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The Shetland HVDC Link, including the onshore converter station at Kergord in Shetland and the new switching station at Noss Head in Caithness, was commissioned in August 2024, following final energisation of the 260 km subsea cable and completion of associated works, thereby connecting Shetland to the Great British electricity grid for the first time.