Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
As part of the Shetland HVDC Link project between Weisdale Voe in Shetland and Noss Head in Caithness, SSEN Transmission and contractor NKT scheduled a combined marine survey for engineering and UXO along the subsea cable route to start in Q2 2021, with an estimated duration of around 45 days, to inform detailed route engineering and subsequent offshore construction activities.