Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable landfall works at Weisdale Voe on Shetland, including excavation of a nearshore trench, installation of polyethylene ducts from the onshore transition joint bay to an exit point in around 10 m water depth, and subsequent pull‑in of the bundled HVDC and fibre‑optic cables through these ducts, were scheduled to be completed in Q2 2023.