Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The Shetland HVDC Link’s 260 km HVDC subsea cable system between the Kergord converter station in Shetland and the Noss Head switching station in Caithness was fully installed in three offshore campaigns during 2022 and 2023, with SSEN reporting that the final section of cable was laid on the seabed in autumn 2023, meaning the complete HVDC cable was in place by the end of 2023.