Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Evidence from an Energy Monitor project profile on the Sheringham Shoal offshore wind farm states that construction of the project began in June 2009 with onshore cable laying works, and that construction of the new Salle onshore substation started in September 2009. These works correspond to the start of onshore construction of the 132 kV land cable system and Salle substation that form the Sheringham Shoal offshore transmission assets.