By 2009, Scira Offshore Energy Limited had signed all required grid connection agreements with National Grid Electricity Transmission under the CUSC framework—including a Bilateral Embedded Generator Agreement (BEGA), a CUSC Accession Agreement and a CUSC Construction Agreement—covering the transmission connection for the Sheringham Shoal offshore transmission assets into the GB system. These agreements satisfied the grid-connection related qualifying pre-conditions for the Sheringham Shoal OFTO transitional project.