Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By June 2009, Scira had completed detailed design and engineering studies, cost optimisation and environmental assessments for the Sheringham Shoal transmission infrastructure, finalising the electrical infrastructure design comprising two offshore substation platforms each with 132 kV GIS and 132/33 kV transformers, separate 132 kV submarine and land export cables to the Salle 132 kV substation, and associated reactive compensation equipment.