Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By the end of July 2011 the Sheringham Shoal transmission assets (offshore platforms, subsea export cables, onshore export cables and onshore substation) had been fully constructed and commissioned, such that the system was fit for use for the transmission of electricity. Ofgem’s cost assessment notes that interest during construction was only allowable up to this point, as the transmission system had been commissioned and was therefore operational as a complete transmission system from late July 2011.