Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By July 2020, Equinor had completed environmental constraints mapping within a 3 km search area near Norwich Main substation, identifying zones with greatest potential for the onshore substation for SEP and DEP and, after assessing 17 options, shortlisting five fields that were presented at the phase one consultation.