Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By January 2019, initial tenders had been returned for the Seagreen Electrical System Integration package covering the transmission works, with bids based on a 275 kV / 1,500 MW solution for the onshore and offshore substations and export cables. Selected tenderers were then asked to update their prices for a revised 220 kV / 1,075 MW configuration, marking a key procurement milestone in refining the scope and commercial terms for the assets that became the Seagreen Phase 1 OFTO.